Expansion of Hong Kong International Airport into a Three-Runway System |
Contents
Figures
Figure 2.1 –
Water Quality Monitoring Stations for Baseline Monitoring
Appendices
Appendix
1.1 – Construction Programme for Marine Works
Appendix 2.1
– Calibration Certificates
Appendix
3.1 – Baseline Water Quality Monitoring Results
Appendix
3.2 – Graphical Presentations of Baseline Water Quality Monitoring Results
Executive Summary
An Environmental Permit (Permit No.:
EP-489/2014) for the construction and operation of the “Expansion of Hong Kong
International Airport into a Three-Runway System” (the project) was granted by
the Environmental Protection Department (EPD) on 7 November 2014.
Mott MacDonald Hong Kong Limited (MMHK) was
commissioned by the Airport Authority Hong Kong (AAHK) to undertake the role of
Environmental Team (ET) for carrying out the environmental monitoring and audit
(EM&A) works of the project.
On 29 April 2016, AAHK received the Chief
Executive-in-Council’s approval for draft Chek Lap Kok Outline Zoning Plan, as well as the authorization of
the reclamation under the Foreshore and Sea-bed (Reclamations) Ordinance for
the expansion of HKIA into a three-runway system.
A Baseline Water Quality Monitoring Report was
prepared for submission before the commencement of marine construction works to
fulfil Condition 3.4 of the EP.
The commencement of initial works was announced
on 1 August 2016. A Baseline Water Quality Report which covers the baseline
monitoring data collection in May and July 2016 was submitted to EPD.
While no marine construction works was undertaken
during August and September 2016, general water quality monitoring was
undertaken in these two months. It was therefore proposed to adopt the
water quality monitoring data collected in August and September 2016 to update
the baseline water quality in order to further improve the baseline data to
take into account potential variations within a year due to natural
fluctuations of dissolved oxygen and also enhance the representativeness of
other water quality monitoring parameters. For this, a Proposal for Review of
Baseline Water Quality was submitted to and subsequently approved by EPD.
This Baseline Water Quality Monitoring Report
presents all the water quality monitoring data obtained in May, July, August
and September 2016.
Baseline Water Quality Monitoring
Baseline water quality monitoring
was conducted three days per week, at mid-flood and mid ebb tides, at 23 water quality monitoring
stations. Monitoring of
DO, DO%, pH, temperature, turbidity, salinity and SS as well as current speed
and direction were undertaken at all monitoring stations. For monitoring of DCM
works, baseline monitoring of total alkalinity, heavy metals and nutrients were
conducted at designated DCM-specific monitoring stations. As no marine
construction works was conducted during the baseline water quality monitoring,
the water quality monitoring results obtained are considered to be appropriate
for adoption as the baseline water quality dataset for the 3RS project.
Action and Limit Levels
The Action and Limit levels for water quality
impact monitoring have been set based on the 3RS baseline water quality
monitoring conducted in May, July, August, and September 2016. The summary table of the Action and Limit levels for water quality are presented in Table I to
Table III.
Table
I: Action
and Limit Levels for General
Impact Water Quality Monitoring and Regular DCM Monitoring
Parameters |
Action Level |
Limit Level |
||
DO in mg/L (Surface, Middle & Bottom) |
Surface and Middle 4.5 mg/L |
Surface and Middle 4.1 mg/L 5 mg/L for Fish Culture Zone (SR7) only |
||
Bottom 3.4 mg/L |
Bottom 2.7 mg/L |
|||
Suspended Solids (SS) in mg/L |
23 |
or 120% of upstream control station at the same tide of the same day, whichever is higher |
37 |
or 130% of upstream control station at the same tide of the same day, whichever is higher |
Turbidity in NTU |
22.6 |
36.1 |
||
Total Alkalinity in ppm |
95 |
99 |
||
Representative Heavy Metals for early regular DCM monitoring (Chromium and Nickel) |
Same as for intensive DCM monitoring |
Same as for intensive DCM monitoring |
||
Representative Heavy Metals for regular DCM monitoring after completion of initial intensive DCM monitoring (to be determined taking into account the findings of the initial intensive DCM monitoring) |
Note:
1. For DO measurement, non-compliance occurs when
monitoring result is lower than the limits.
2. For parameters other than DO, non-compliance of
water quality results when monitoring results is higher than the limits.
3. Depth-averaged results are used unless
specified otherwise.
4. The action and limit levels specified in this
table does not apply to SR1A and SR8 (see Section 4.2).
5. The action and limit levels for the two
representative heavy metals chosen will be the same as that for the intensive
DCM monitoring
Table
II: Action
and Limit Levels for Intensive DCM Monitoring
Parameters |
Action Level |
Limit Level |
||
Temperature in °C
|
1.8°C above the temperature recorded at representative control stations at the same tide of the same day |
2°C above the temperature recorded at representative control stations at the same tide of the same day |
||
Total Alkalinity in ppm |
95 |
or 120% of upstream control station at the same tide of the same day, whichever is higher |
99 |
or 130% of upstream control station at the same tide of the same day, whichever is higher |
Nutrient (mg/l) |
|
|
||
Ammonia (NH3) |
0.18 |
0.20 |
||
Unionised ammonia (NH3) (with 0.021 mg/L as the upper limit) |
0.01 |
0.01 |
||
Nitrite (NO2) |
0.12 |
0.13 |
||
Nitrate (NO3) |
1.05 |
1.18 |
||
TKN |
0.6 |
0.7 |
||
Total Phosphorus |
0.06 |
0.07 |
||
Reactive Phosphorus |
0.04 |
0.04 |
||
Heavy Metals (µg/l) |
|
|
||
Cadmium (Cd) |
0.1 |
0.1 |
||
Chromium (Cr) |
0.2 |
0.2 |
||
Copper (Cu) |
1.9 |
5.1 |
||
Nickel (Ni) |
3.2 |
3.6 |
||
Lead (Pb) |
0.2 |
0.2 |
||
Zinc (Zn) |
6 |
8 |
||
Arsenic (As) |
3 |
4 |
||
Silver (Ag) |
0.1 |
0.1 |
||
Mercury (Hg) |
0.05 |
0.05 |
Note:
1. Non-compliance of water quality results when
monitoring results is higher than the limits.
2. Depth-averaged results are used unless
specified otherwise.
3. For Cd, Cr, Pb, Ag and
Hg, the percentile values are below detection limit, hence the Action and Limit
levels represent detection limit.
4. Where the water quality results at control
stations for individual parameters are below detection limit, the value of the
detection limit will be adopted.
Table
III: Action and Limit
Levels for SR1 and SR8
SS (mg/l) |
Action Level |
Limit Level |
SR1 |
To be determined prior to its commissioning |
To be determined prior to its commissioning |
SR8 |
52 |
60 |
Should
non-compliance of the water quality criteria occur, the Event and Action Plan
as presented in Section 4.3 of this report (for general impact water
quality monitoring) and in the Detailed Plan on Deep Cement Mixing (for DCM
monitoring) shall be followed.
On 7 November 2014, the Environment Impact
Assessment (EIA) Report (Register No.: AEIAR-185/2014) for the “Expansion of
Hong Kong International Airport into a Three-Runway System” (the project) was
approved and an Environmental Permit (EP) (Permit No.: EP-489/2014) was issued
for the construction and operation of the project.
On 29 April 2016, AAHK received the Chief
Executive-in-Council’s approval for draft Chek Lap Kok Outline Zoning Plan, as well as the authorization of
the reclamation under the Foreshore and Sea-bed (Reclamations) Ordinance for
the expansion of HKIA into a three-runway system.
Mott MacDonald Hong Kong Limited (MMHK) was
commissioned by the Airport Authority Hong Kong (AAHK) to serve as the project’s
Environmental Team (ET) for carrying out the environmental monitoring and audit
(EM&A) works of the project.
A Baseline Water Quality Monitoring Report was
prepared for submission before the commencement of marine construction works to
fulfil Condition 3.4 of the EP.
The commencement of initial works was announced
on 1 August 2016. A Baseline Water Quality Report which covers the baseline
monitoring data collection from 3 to 14 May 2016 and from 19 to 30 July 2016
was submitted to EPD.
As stated in the Monthly Environmental
Monitoring & Audit (EM&A) Report No. 8 (for August 2016) and Report No.
9 (for September 2016) submitted for the project, the key marine activities
included mobilization and off-site plant fabrication for the DCM contracts, CLP
cable diversion enabling works, site investigation works and site survey. No
marine construction works was undertaken during August and September 2016.
However, general water quality monitoring was undertaken in accordance with the
requirements provided in the EM&A Manual for impact water quality
monitoring for August and September 2016. It was therefore proposed to
adopt the water quality monitoring data collected in these two months to update
the baseline water quality in order to further improve the baseline data to
take into account potential variations within a year due to natural
fluctuations of dissolved oxygen and also enhance the representativeness of
other water quality monitoring parameters. For this, a Proposal for
Review of Baseline Water Quality was submitted to and subsequently approved by
EPD.
The project covers the expansion of the
existing airport into a three-runway system with key project components
comprising land formation of about 650 ha and all associated facilities and
infrastructure including taxiways, aprons, aircraft stands, a passenger
concourse, an expanded Terminal 2, all related airside and landside works and
associated ancillary and supporting facilities. The existing submarine
aviation fuel pipelines and submarine power cables also require diversion as
part of the works.
The current construction programme for marine
works is provided in Appendix
1.1 and it has been prepared based on the best available information.
Given the scale and complexity of the project, the details of the programme as
presented is subject to further revision and update.
This Baseline Water Quality Monitoring Report
presents all the water quality monitoring data obtained in May, July, August
and September 2016. The baseline water quality monitoring has been undertaken
based on the approach and methodology presented in the updated EM&A Manual.
The
structure of the report is as follows:
● Section 1 Introduction – presents
the project background, purpose and structure of this baseline water quality
monitoring report;
● Section 2 Water Quality Monitoring Methodology
– presents the monitoring requirements and methodology on baseline water
quality monitoring;
● Section 3 Baseline Monitoring
Results and Analysis – presents the baseline monitoring results and the
findings of the statistical analysis;
● Section 4 Event and Action Plan –
presents the action and limit levels as well as event and action plan for
impact water quality monitoring.
In accordance with the updated
EM&A Manual, the baseline
water quality monitoring was conducted to establish ambient conditions prior to
the commencement of the marine works. The baseline conditions for water quality
were established by measuring dissolved oxygen (DO), dissolved oxygen
saturation (DO%), pH, temperature, turbidity, salinity, and suspended solids
(SS) at all designated stationary monitoring stations before
commencement of marine works for the project. To provide the baseline water quality for the DCM-specific monitoring,
total alkalinity was measured at all the relevant stationary impact stations,
plus nutrients and heavy metals at the “IM*” stations (which represent the
contaminated mud pit locations) as presented in Section 2.5.
Water samples for all monitoring parameters
were collected, stored, preserved and analysed according to the Standard
Methods, APHA 22nd ed. and/or other methods as agreed by the EPD.
In-situ measurements at monitoring locations including temperature, pH, DO,
turbidity, salinity and water depth were collected by equipment listed in the
following Table 2.1. Water samples for
nutrients, heavy metals and SS analysis were stored in high density polythene
bottles with no preservative added, packed in ice (cooled to 4 ºC without being
frozen), delivered to the laboratory within 24 hours of collection.
Table 2.1:
Baseline Water Quality Monitoring Equipment
Equipment |
Brand and Model |
Quantity |
Water Sampler |
Van Dorn Water Sampler |
4 |
Positioning Device (measurement of GPS) |
Garmin eTrex Vista HCx |
2 |
Water Depth Detector (measurement of water depth) |
Lowrance Mark 5x |
2 |
Multifunctional Meter (measurement of DO, pH, temperature, salinity and turbidity) |
YSI 6920 |
2 |
Current Meter (measurement of current speed and direction) |
Sontek HydroSurveyor |
2 |
Digital Titrator (measurement of total alkalinity) |
Titrette Digital Burette 50ml Class A |
2 |
Calibration
of In-situ instruments
All in-situ monitoring instrument were checked,
calibrated and certified by a laboratory accredited under HOKLAS before use.
Responses of sensors and electrodes were checked with certified standard
solutions before each use.
Wet bulb calibration for a DO meter was carried
out before commencement of monitoring and after completion of all measurements
each day. Calibration was not conducted at each monitoring location as daily
calibration is adequate for the type of DO meter employed. A zero check in
distilled water was performed with the turbidity probe at least once per
monitoring day. The probe should then be calibrated with a solution of known
NTU. In addition, the turbidity probe was calibrated at least twice per month
to establish the relationship between turbidity readings (in NTU) and levels of
suspended solids (in mg/L). Accuracy check of the digital titrator was performed at least once per monitoring day.
Calibration certificates of the
monitoring equipment used in the baseline monitoring are provided in Appendix
2.1.
Analysis
of SS, nutrients and heavy metals have been carried out by a HOKLAS accredited
laboratory, ALS Technichem (HK) Pty Ltd (Reg. No.
HOKLAS 066). Sufficient water samples were collected at all the monitoring
stations for carrying out the laboratory SS, nutrients and heavy metals
determination. The SS, nutrients and heavy metals determination works were started
within 24 hours after collection of the water samples. The analysis of SS,
nutrients and heavy metals have followed the standard methods summarised in Table 2.2.
Table 2.2:
Laboratory Analysis for SS, Nutrient and Heavy Metals
Parameters |
Instrumentation |
Analytical Method |
Reporting Limit |
Suspended Solid (SS) |
Analytical Balance |
APHA 2540D |
2 mg/L |
Nutrients |
|
|
|
Ammonia as N |
FIA |
APHA 4500 |
0.01 mg/L |
Unionised ammonia (NH3)* |
By calculation |
By calculation |
By calculation |
Nitrite as N |
FIA |
APHA 4500 |
0.01 mg/L |
Nitrate as N |
FIA |
APHA 4500 |
0.01 mg/L |
TKN as N |
Titration |
APHA 4500 |
0.1 mg/L |
Total Phosphorus |
Colorimetric |
APHA 4500 |
0.01 mg/L |
Reactive Phosphorus |
FIA |
APHA 4500 |
0.01 mg/L |
Heavy Metals |
|
|
|
Cadmium (Cd) |
ICP-MS |
USEPA 6020A |
0.1 µg/L |
Chromium (Cr) |
ICP-MS |
USEPA 6020A |
0.2 µg/L |
Copper (Cu) |
ICP-MS |
USEPA 6020A |
0.2 µg/L |
Nickel (Ni) |
ICP-MS |
USEPA 6020A |
0.2 µg/L |
Lead (Pb) |
ICP-MS |
USEPA 6020A |
0.2 µg/L |
Zinc (Zn) |
ICP-MS |
USEPA 6020A |
1 µg/L |
Arsenic (As) |
ICP-MS |
USEPA 6020A |
1 µg/L |
Silver (Ag) |
ICP-MS |
USEPA 6020A |
0.1 µg/L |
Mercury (Hg) |
ICP-MS |
APHA 7470A |
0.05 µg/L |
*Note:
Calculation based on the laboratory result of ammonia
nitrogen (NH4-N) and in-situ measured pH, salinity and temperature.
To account for potential variations within a year, the
baseline was conducted in May (from 3 to 14 May 2016), July (from 19 to 30 July
2016), August (from 4 to 30 August 2016) and September (from 1 to 29 September
2016).
The baseline water quality monitoring was
conducted three days per week, at mid-flood and mid-ebb tides, at 23 water
quality monitoring stations. Samples were taken at three depths (at 1m below
surface, at mid-depth, and at 1m above bottom) for locations with water depth
>6m. For locations with water depth between 3m and 6m, water samples were
taken at two depths (surface and bottom). For locations with water depth
<3m, only the surface depth was taken. Duplicate water samples were taken
and analysed.
The baseline monitoring was conducted at a
total of 23 water quality monitoring stations, comprising 12 impact stations,
eight sensitive receiver stations and three control stations. The monitoring
locations for baseline monitoring are shown in Table 2.3.
Alternative Monitoring Locations
Based on the provisions and requirements set
out in Section 5.1.5 of the Updated EM&A Manual, changes in monitoring
locations were proposed for SR1, SR4 and SR5. Agreement from the IEC and
approval from the EPD were sought for the changes. The locations of the
alternative monitoring stations, including SR1A, SR4A and SR5A, are shown in
Figure 2.1.
Table 2.3 summarises the updated coordinates of
the alternative monitoring locations.
Temporary Alternative Monitoring
Location for SR1
A temporary change of the monitoring location
for SR1 was identified necessary as a silt curtain was
installed at the waters blocking access to SR1. Therefore, the proposed
temporary monitoring location (SR1A) is slightly shifted to around 159 m to the
west of SR1. The temporary alternative monitoring station at SR1A is the
closest accessible location to the future permanent SR1. Given the constraints
identified, the change of location to SR1A is considered to be the best
practicable and representative location for baseline water quality monitoring
at this water sensitive receiver.
It should be noted that SR1/SR1A is
used to represent the seawater intake for the future HKBCF, however, this
seawater intake is not yet in operation and therefore the future permanent
location for SR1 during impact monitoring is subject to
finalisation after the HKBCF seawater intake is commissioned.
Permanent Alternative Monitoring
Locations for SR4 and SR5
Changes of the monitoring locations for SR4 and
SR5 were required as the water depths around the original monitoring locations
at SR4 and SR5 were found to be too shallow (less than 1.5m). The alternative
monitoring locations at SR4A and SR5A are outside the shallow waters, i.e.,
with sufficient water depths for access by the sampling vessel (with a draft of
about 2.5m). The alternative monitoring locations are the closest and
accessible locations to the bay areas of the two WSRs. Hence, they are
considered to be practicable and representative locations for monitoring the
construction phase water quality impact at the WSRs.
The final coordinates of the monitoring
stations for baseline monitoring are shown in Table 2.3
and their locations are shown in Figure 2.1.
Table 2.3:
Monitoring Locations for Baseline Water Quality Monitoring
Monitoring Stations |
|
Coordinates |
|
Description |
Easting |
Northing |
|
C1 |
Control |
804247 |
815620 |
C2 |
Control |
806945 |
825682 |
C3 |
Control |
817803 |
822109 |
IM1 |
Impact |
806458 |
818351 |
IM2 |
Impact |
806193 |
818852 |
IM3 |
Impact |
806019 |
819411 |
IM4 |
Impact |
805039 |
819570 |
IM5 |
Impact |
804924 |
820564 |
IM6 |
Impact |
805828 |
821060 |
IM7 |
Impact |
806835 |
821349 |
IM8 |
Impact |
807838 |
821695 |
IM9* |
Impact |
808811 |
822094 |
IM10* |
Impact |
809838 |
822240 |
IM11* |
Impact |
810545 |
821501 |
IM12* |
Impact |
811519 |
821162 |
SR1A(1) |
Future Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) Seawater Intake for cooling |
812586 |
820069 |
SR2 |
Planned marine park / hard corals at The Brothers / Tai Mo To |
814166 |
821463 |
SR3 |
Sha Chau and Lung Kwu Chau Marine Park / fishing and spawning grounds in North Lantau |
807571 |
822147 |
SR4A(1) |
Sha Lo Wan |
807810 |
817189 |
SR5A(1) |
San Tau Beach SSSI |
810696 |
816593 |
SR6 |
Tai Ho Bay, Near Tai Ho Stream SSSI |
814663 |
817899 |
SR7 |
Ma Wan Fish Culture Zone (FCZ) |
823742 |
823636 |
SR8 |
Seawater Intake for cooling at Hong Kong International Airport (East) |
811593 |
820417 |
Notes:
* Denotes baseline monitoring
stations and/or parameters for DCM-specific monitoring
(1) Alternative monitoring location
Monitoring of DO, DO%, pH, temperature, turbidity,
salinity and SS as well as current speed and direction were undertaken at all
monitoring stations. For monitoring of DCM works, baseline monitoring of total
alkalinity, heavy metals and nutrients were conducted at designated
DCM-specific monitoring stations.
The monitoring parameters in May and July 2016
as well as in August and September 2016 are summarised respectively in Table 2.4 and Table 2.5.
Table 2.4:
Summary of Monitoring Stations and Parameters (May and July 2016)
Monitoring Stations |
Type |
Parameters Monitored |
C1, C2, C3 |
Control |
DO, pH, Temperature, Salinity, Turbidity, SS |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8 |
Impact |
DO, pH, Temperature, Salinity, Turbidity, SS Total Alkalinity |
IM9, IM10, IM11, IM12 |
Impact |
DO, pH, Temperature, Salinity, Turbidity, SS Total Alkalinity, Heavy Metals, Nutrients |
SR1A, SR2, SR3, SR4A, SR5A, SR6, SR7, SR8 |
Sensitive Receiver |
DO, pH, Temperature, Salinity, Turbidity, SS |
Table 2.5:
Summary of Monitoring Stations and Parameters (August and September 2016)
Monitoring Stations |
Type |
Parameters Monitored |
C1, C2, C3, SR2* |
Control |
DO, pH, Temperature, Salinity, Turbidity, SS Total Alkalinity, Chromium, Nickel |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, IM9, IM10, IM11, IM12 |
Impact |
DO, pH, Temperature, Salinity, Turbidity, SS Total Alkalinity, Chromium, Nickel |
SR1A, SR3, SR4A, SR5A, SR6, SR7, SR8 |
Sensitive Receiver |
DO, pH, Temperature, Salinity, Turbidity, SS |
*Note:
SR2 replaces C3 as the flood tide control station (refer to Section 3.2
for details), and monitoring of total alkalinity, chromium and nickel commenced
at SR2 starting in September 2016.
Detailed baseline water quality
monitoring results in
May, July, August and September 2016 are tabulated
and presented in Appendix
3.1. Graphical presentations of the baseline monitoring results are
provided in Appendix
3.2.
General weather conditions
throughout the baseline water quality monitoring period were recorded. The
collected data are presented in Appendix
3.1. The weather conditions were mainly fine and cloudy, and the sea
conditions were mainly moderate throughout the baseline monitoring period.
As no marine construction works was conducted
during the baseline water quality monitoring, the water quality monitoring
results obtained are considered to be appropriate for adoption as the baseline
water quality dataset for the project.
To analyse if there is any significant
difference between control and impact stations, statistical analysis was
conducted to compare the findings from the control station versus those from
the impact / sensitive receiver stations. During baseline monitoring, DO, DO%,
pH, temperature, salinity, turbidity and SS were monitored at the control
stations, however, only turbidity and SS are linked to control station results
during impact monitoring with respect to Action and Limit levels. As such, the
statistical analysis was conducted for turbidity and SS only.
Statistical Analysis of Data Collected in May
and July 2016
In the submission to EPD which covers the
baseline monitoring data collected in May and July 2016 (see Section 1.1),
statistical analysis of the collected data using one-way analysis of variance
(ANOVA) was conducted. Impact stations were grouped according to corresponding
control stations under flood tide and ebb tide conditions. The results of the
ANOVA test are presented in Table 3.1.
Table 3.1:
Results of ANOVA Test (May and July 2016)
ANOVA Test Groups |
P-value (alpha = 0.05) |
||
Control Station |
Impact Stations |
SS |
Turbidity |
Flood Tide |
|
|
|
C1 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, SR3 |
0.02 |
0.16 |
C3 |
IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR2, SR3, SR4A, SR5A, SR6, SR8 |
0.08 |
0.01 |
Ebb Tide |
|
|
|
C1 |
SR4A, SR5A, SR6 |
0.42 |
0.87 |
C2 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR2, SR3, SR7, SR8 |
0.11 |
0.73 |
Note:
bold values show statistically significant difference between control and
impact stations
As shown in Table 3.1,
significant difference is identified between C1 and its corresponding impact
stations for SS during flood tide, and between C3 and its corresponding impact
stations for turbidity during flood tide. No significant difference was
identified for the other combinations, hence only the significant differences
affecting C1 and C3 during flood tide were further evaluated.
At C1, the depth-averaged SS results during
flood tide range from 5 to 43 mg/l, while those of the impact stations range
from 3 to 40 mg/l. On average, the SS results at C1 are higher than the impact
stations, due primarily to the presence of several high SS results at C1. If
the highest and lowest C1 results are excluded from the ANOVA test, then the
resulting P-value would be 0.07 (no significant difference). This suggests that
the significant difference identified in Table 3.1
is a result of the extreme values rather than reflecting the majority of the C1
results. Extreme values can arise due to natural fluctuations in the marine
environment, and given that in the absence of these extremes, the C1 results
would show no significant difference with the impact stations, it is considered
that overall, this control station is acceptable and
representative for the purpose of impact monitoring.
At C3, the depth-averaged turbidity results
during flood tide range from 3.2 to 12.6 mg/l, while those of the impact
stations range from 3.9 to 51.7 mg/l. The results at C3 are significantly lower
than the majority of the impact station results, suggesting that the location
of C3 is unable to adequately represent the water quality at the impact
stations under baseline conditions during flood tide. In this case, an
alternative control station location to cover flood tide (for corresponding
impact stations as shown in Table 3.1) is
required. As shown in Figure 2.1,
both C3 and SR2 are located upstream of the project during flood tides, and SR2
is located >2.7 km away from the marine works area of the project, hence is
similar to C3 in that it is unaffected by marine works of the project during
flood tide conditions. As SR2 is unaffected by the project during flood tide,
it can effectively act as a control station during flood tide conditions. An
ANOVA test using SR2 as control against the impact group (IM7, IM8, IM9, IM10,
IM11, IM12, SR1A, SR3, SR4A, SR5A, SR6, SR8) was
conducted and the resulting P-values are 0.58 and 0.89 for turbidity and SS
respectively, which show that there is no significant difference. Hence,
the SR2 location is able to represent the water quality at these impact
stations during flood tide under baseline conditions.
The refined ANOVA test results are summarised
in Table 3.2.
Table 3.2:
Refined Results of ANOVA Test (May and July 2016)
ANOVA Test Groups |
P-value (alpha = 0.05) |
||
Control Station |
Impact Stations |
SS |
Turbidity |
Flood Tide |
|
|
|
C1 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, SR3 |
0.07* |
0.16 |
SR2 |
IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR3, SR4A, SR5A, SR6, SR8 |
0.89 |
0.58 |
Ebb Tide |
|
|
|
C1 |
SR4A, SR5A, SR6 |
0.42 |
0.87 |
C2 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR2, SR3, SR7, SR8 |
0.11 |
0.73 |
Note: (*) excludes the highest
and lowest values for SS at C1 during flood tide.
Statistical Analysis of Data Collected in
August and September 2016
Statistical analysis using the same approach as
mentioned above was conducted for the water quality monitoring data collected
in August and September 2016. The refined ANOVA test results are
presented in Table 3.3.
Table 3.3:
Refined ANOVA Test Results (August and September 2016)
ANOVA Test Groups |
P-value (alpha = 0.05) |
||
Control Station |
Impact Stations |
SS |
Turbidity |
Flood Tide |
|
|
|
C1 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, SR3 |
0.08* |
0.13* |
SR2 |
IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR3, SR4A, SR5A, SR6, SR8 |
0.38 |
0.08 |
Ebb Tide |
|
|
|
C1 |
SR4A, SR5A, SR6 |
0.54 |
0.64 |
C2 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR2, SR3, SR7, SR8 |
0.46 |
0.83 |
Note: (*) excludes the highest
and lowest values for SS and turbidity at C1 during flood tide.
As shown in Table 3.3,
there is no significant difference between the control and impact stations.
Summary
In view of the aforementioned ANOVA test
results, the final arrangement for the control and impact station groups under
flood and ebb tide conditions are presented in Table 3.4.
Table 3.4:
Final Arrangement of Control and Impact Stations
Control Station |
Impact Stations |
Flood Tide |
|
C1 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, SR3 |
SR2 |
IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR3, SR4A, SR5A, SR6, SR8 |
Ebb Tide |
|
C1 |
SR4A, SR5A, SR6 |
C2 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR2, SR3, SR7, SR8 |
The baseline water quality monitoring data
collected in May, July, August and September 2016 was used to determine the
Action and Limit levels, using the derivation criteria specified in the updated
EM&A Manual.
The presence of any outliers was checked,
whereby the range of depth-averaged data (except for dissolved oxygen which
separates surface and middle level data from bottom level data) are compared
and those that do not conform to the dataset range as a whole are removed.
Using this approach, two notably high depth-averaged results for suspended
solids were identified as outliers (as shown in Appendix
3.1 and Appendix
3.2), and have been removed from the dataset used to determine Action
and Limit levels.
Table 4.1:
Action and Limit Levels for General Impact Water Quality Monitoring and Regular DCM
Monitoring
Parameters |
Action Level |
Limit Level |
||
DO in mg/L (Surface, Middle & Bottom) |
Surface and Middle 4.5 mg/L |
Surface and Middle 4.1 mg/L 5 mg/L for Fish Culture Zone (SR7) only |
||
Bottom 3.4 mg/L |
Bottom 2.7 mg/L |
|||
Suspended Solids (SS) in mg/L |
23 |
or 120% of upstream control station at the same tide of the same day, whichever is higher |
37 |
or 130% of upstream control station at the same tide of the same day, whichever is higher |
Turbidity in NTU |
22.6 |
36.1 |
||
Total Alkalinity in ppm |
95 |
99 |
||
Representative Heavy Metals for early regular DCM monitoring (Chromium and Nickel) |
Same as for intensive DCM monitoring |
Same as for intensive DCM monitoring |
||
Representative Heavy Metals for regular DCM monitoring after completion of initial intensive DCM monitoring (to be determined taking into account the findings of the initial intensive DCM monitoring) |
Note:
1. For DO measurement, non-compliance occurs when
monitoring result is lower than the limits.
2. For parameters other than DO, non-compliance of
water quality results when monitoring results is higher than the limits.
3. Depth-averaged results are used unless
specified otherwise.
4. The action and limit levels specified in this
table does not apply to SR1A and SR8 (see Section 4.2).
5. Details of selection criteria for the two heavy
metals for early regular DCM monitoring refer to the Detailed Plan on Deep
Cement Mixing available on the dedicated 3RS website http://env.threerunwaysystem.com/en/ep-submissions.html)
6. The action and limit levels for the two
representative heavy metals chosen will be the same as that for the intensive
DCM monitoring
For intensive DCM monitoring, the Action and
Limit levels to be adopted at the intensive DCM monitoring stations are presented
in Table 4.2.
Table 4.2:
Action and Limit Levels for Intensive DCM Monitoring
Parameters |
Action Level |
Limit Level |
||
Temperature in °C
|
1.8°C above the temperature recorded at representative control stations at the same tide of the same day |
2°C above the temperature recorded at representative control stations at the same tide of the same day |
||
Total Alkalinity in ppm |
95 |
or 120% of upstream control station at the same tide of the same day, whichever is higher |
99 |
or 130% of upstream control station at the same tide of the same day, whichever is higher |
Nutrient (mg/l) |
|
|
||
Ammonia (NH3) |
0.18 |
0.20 |
||
Unionised ammonia (NH3) (with 0.021 mg/L as the upper limit) |
0.01 |
0.01 |
||
Nitrite (NO2) |
0.12 |
0.13 |
||
Nitrate (NO3) |
1.05 |
1.18 |
||
TKN |
0.6 |
0.7 |
||
Total Phosphorus |
0.06 |
0.07 |
||
Reactive Phosphorus |
0.04 |
0.04 |
||
Heavy Metals (µg/l) |
|
|
||
Cadmium (Cd) |
0.1 |
0.1 |
||
Chromium (Cr) |
0.2 |
0.2 |
||
Copper (Cu) |
1.9 |
5.1 |
||
Nickel (Ni) |
3.2 |
3.6 |
||
Lead (Pb) |
0.2 |
0.2 |
||
Zinc (Zn) |
6 |
8 |
||
Arsenic (As) |
3 |
4 |
||
Silver (Ag) |
0.1 |
0.1 |
||
Mercury (Hg) |
0.05 |
0.05 |
Note:
1. Non-compliance of water quality results when
monitoring results is higher than the limits.
2. Depth-averaged results are used unless
specified otherwise.
3. For Cd, Cr, Pb, Ag and
Hg, the percentile values are below detection limit, hence the Action and Limit
levels represent detection limit.
4. Where the water quality results at control
stations for individual parameters are below detection limit, the value of the detection
limit will be adopted.
According to the updated EM&A Manual,
sensitive receiver stations representing seawater intakes for cooling are
affected by SS only, and hence only the Action and Limit levels for SS
parameter would be applicable. The Action and Limit levels at these intakes
would be determined and agreed with the respective operators of the intakes
prior to commencement of construction activities or commencement of operation
of the seawater intake (whichever is later).
For the 3RS project, the status of the two
seawater intakes for cooling (i.e. SR1 and SR8) at the time of preparation of
this report are summarised below:
SR1 – to be constructed / commissioned. Programme
of commissioning has been delayed (compared to original programme assumed at
the time of approval of 3RS EIA report). Based on latest information from the
project proponent of HKBCF, the earliest commissioning date for this intake is
mid-2017. Operational tolerance for SS is subject to further liaison with the
project proponent of HKBCF.
SR8 – in operation by AAHK. Appropriate Action and
Limit levels have been proposed taking into account the operational tolerance
of the intake and agreed with the operator and IEC.
The Action and Limit levels to be adopted for
these seawater intakes are summarised in Table 4.3.
Table 4.3:
Action and Limit Level for SR1 and SR8
SS (mg/l) |
Action Level |
Limit Level |
SR1 |
To be determined prior to its commissioning |
To be determined prior to its commissioning |
SR8 |
52 |
60 |
For SR1, the Action and Limit levels to be
adopted are subject to further liaison and agreement with the project proponent
of HKBCF. Meanwhile, it is recognised that SR1 is yet to be commissioned, hence
it is not yet an existing sensitive receiver and consequently, would not be
impacted by the 3RS project before it is commissioned. Given these
circumstances, there is no need for conducting impact monitoring at this SR1
location prior to its commissioning date.
Separately, the future permanent monitoring
location of SR1 is subject to further confirmation once the exact location of
SR1 is determined, taking into account the need for silt curtains to be
deployed around this SR1 location as part of the mitigation measures for 3RS
project.
Given the aforementioned issues and programme
mismatch, the final details for SR1 including its monitoring location,
commissioning date and Action and Limit levels will be submitted to EPD prior
to commissioning of the seawater intake at SR1 and documented in the monthly
EM&A Report.
For SR8, it is noted that silt curtains are to
be deployed around this SR8 location as part of the mitigation measures for 3RS
project, while the intake itself is located within the works boundary of the
3RS project and will need to be relocated during construction phase. As such,
the impact monitoring location for SR8 will be subject to further changes.
Where the monitoring location needs to be updated, the updated location shall
be notified to IEC and EPD and documented in the monthly EM&A Report.
For general impact water quality monitoring,
should non-compliance of the water quality criteria occur, the Event and Action
Plan as presented in Table 4‑4 shall be
followed. For DCM monitoring, the Event and Action Plan shall follow the
Detailed Plan on Deep Cement Mixing, which can be accessed from http://env.threerunwaysystem.com/en/ep-submissions.html.
The Event and Action Plan for the initial intensive DCM monitoring presented in
the Detailed Plan on Deep Cement Mixing submitted under EP condition 2.17 shall
be followed during the initial intensive DCM monitoring stage.
Table 4‑4:
Event and Action Plan for General Impact Water Quality Monitoring
|
Action |
|||
Event |
ET |
IEC |
AAHK / PM |
Contractor |
Action level being exceeded by one sampling day |
1. Repeat in-situ measurement to confirm findings; 2. Identify reasons for non-compliance and sources of impact; 3. Inform IEC and Contractor; 4. Check monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss mitigation measures with IEC and Contractor; 6. Repeat in-situ monitoring on the day after the exceedance. |
1. Discuss with ET and Contractor on the mitigation measures; 2. Review proposals on mitigation measures submitted by Contractor and advise AAHK / PM accordingly; 3. Assess the effectiveness of the implemented mitigation measures. |
1. Discuss with IEC on the proposed mitigation measures; 2. Make agreement on the mitigation measures to be implemented; 3. Assess the effectiveness of the implemented mitigation measures. |
1. Inform AAHK / PM and confirm receipt of ET’s notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Provide report of the status and condition of plant, equipment and mitigation measures to ET 5. Consider changes of working methods; 6. Discuss with ET and IEC and propose mitigation measures. |
Action Level being exceeded by more than two consecutive sampling days |
1. Repeat in-situ measurement to confirm findings; 2. Identify reasons for non-compliance and sources of impact; 3. Inform IEC and Contractor; 4. Check monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss mitigation measures with IEC and Contractor; 6. Ensure mitigation measures are implemented; 7. Repeat in-situ monitoring on the day after the exceedance and prepare to increase the monitoring frequency to daily. |
1. Discuss with ET and Contractor on the mitigation measures; 2. Review proposals on mitigation measures submitted by Contractor and advise AAHK / PM accordingly; 3. Assess the effectiveness of the implemented mitigation measures. |
1. Discuss with IEC on the proposed mitigation measures; 2. Make agreement on the mitigation measures to be implemented; 3. Assess the effectiveness of the implemented mitigation measures. |
1. Inform AAHK / PM and confirm receipt of ET’s notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Provide report of the status and condition of plant, equipment and mitigation measures to ET 5. Consider changes of working methods; 6. Discuss with ET and IEC and propose mitigation measures to IEC and AAHK / PM within three working days; 7. Implement the agreed mitigation measures.
|
Limit Level being exceeded by one sampling day |
1. Repeat in-situ measurement to confirm findings; 2. Identify reasons for non-compliance and sources of impact; 3. Inform IEC, Contractor and EPD; 4. Check monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss mitigation measures with IEC, AAHK / PM and Contractor; 6. Ensure mitigation measures are implemented; 7. Repeat in-situ monitoring on the day after the exceedance and prepare to increase the monitoring frequency to daily |
1. Discuss with ET and Contractor on the mitigation measures; 2. Review proposals on mitigation measures submitted by Contractor and advise AAHK / PM accordingly; 3. Assess the effectiveness of the implemented mitigation measures. |
1. Discuss with IEC, ET and Contractor on the proposed mitigation measures; 2. Request Contractor to critically review the working methods; 3. Make agreement on the mitigation measures to be implemented; 4. Assess the effectiveness of the implemented mitigation measures. |
1. Inform AAHK / PM and confirm receipt of ET’s notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Provide report of the status and condition of plant, equipment and mitigation measures to ET 5. Consider changes of working methods; 6. Discuss with ET, IEC and AAHK / PM and propose mitigation measures to IEC and AAHK / PM within three working days; 7. Implement the agreed mitigation measures. |
Limit Level being exceeded by more than one consecutive sampling days |
1. Repeat in-situ measurement to confirm findings; 2. Identify reasons for non-compliance and sources of impact; 3. Inform IEC, Contractor and EPD; 4. Check monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss mitigation measures with IEC, AAHK / PM and Contractor; 6. Ensure mitigation measures are implemented; 7. Increase the in-situ monitoring frequency to daily until no exceedance of limit level for two consecutive days. |
1. Discuss with ET and Contractor on the mitigation measures; 2. Review proposals on mitigation measures submitted by Contractor and advise AAHK / PM accordingly; 3. Assess the effectiveness of the implemented mitigation measures. |
1. Discuss with IEC, ET and Contractor on the proposed mitigation measures; 2. Request contractor to critically review the working methods; 3. Make agreement on the mitigation measures to be implemented; 4. Assess the effectiveness of the implemented mitigation measures; 5. Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the construction activities until no exceedance of limit level. |
1. Inform AAHK / PM and confirm receipt of ET’s notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Provide daily report of the status and condition of plant, equipment and mitigation measures to ET until no further exceedance; 5. Consider changes of working methods; 6. Discuss with ET, IEC and AAHK / PM and propose mitigation measures to IEC and AAHK / PM within three working days; 7. Implement the agreed mitigation measures; 8. As directed by AAHK / PM, to slow down or to stop all or part of the construction activities. |
Note:
Where the action level is the same as the limit level, the actions specified
for limit level exceedances shall apply.
As part of the baseline water quality
monitoring conducted for the 3RS project and its subsequent findings and
recommendations, the following revisions to the Updated EM&A Manual are
recommended.
Table 5.1:
Recommended Revisions to Updated EM&A Manual
Relevant Section in Updated EM&A Manual |
Original Requirement |
Revisions Recommended |
Section 5.1.3.14 |
Wet bulb calibration for a DO meter should be carried out before measurement at each monitoring location |
Wet bulb calibration for a DO meter should be carried out before commencement of monitoring and after completion of all measurements each day |
Table 5-2 |
Water Quality Monitoring Stations (construction and post construction phases) |
Location of SR1 subject to finalisation after the HKBCF seawater intake is commissioned. The final location shall be documented in the monthly EM&A Report |
As SR1 is yet to be commissioned, no impact monitoring will be conducted at SR1 prior to its commissioning date. The final commissioning date, once determined, shall be documented in the monthly EM&A Report |
||
Alternative locations for SR4 and SR5 according to Table 2-3 of this Baseline Report |
||
Table 5-4 |
Event and Action Plan for Water Quality |
Supplementary and updated actions in the Event and Action Plan for Water Quality as per Table 4-4 of this Baseline Report |
Aside from the revisions specified in Table 5.1, other revisions to the Updated EM&A
Manual (e.g. due to other related 3RS submissions such as the Detailed Plan on
Deep Cement Mixing) may also apply.
Baseline water quality monitoring was undertaken
in May, July, August and September 2016 in accordance with the requirements set
out in the EP and the updated EM&A Manual. All monitoring equipment used
were properly calibrated and valid calibration certificates are included in
this report.
To improve the baseline data to take into account
potential variations within a year due to natural fluctuations of dissolved
oxygen and also enhance the representativeness of other water quality
monitoring parameters, the combined water quality data collected in May, July, August and September
2016 was adopted as the baseline dataset. The baseline water quality monitoring was
carried out for three days per week at mid-flood and mid ebb tides, at a total of 23 water quality
monitoring stations. The weather conditions were mainly fine and cloudy, and
the sea conditions were mainly moderate throughout the baseline monitoring
period. The results of baseline monitoring were provided in tables and
graphical presentations in this report. As no marine construction works was
conducted during the baseline water quality monitoring,
the baseline water
quality monitoring results obtained are considered to be appropriate for
adoption as the baseline water quality dataset for the 3RS project. Where
applicable, revisions to the Updated EM&A Manual are recommended.